Delivery Flow Master Checklist (with Documents)

Use this as the single execution gate from SOW → PRD → Delivery.
Columns are designed to map cleanly into Notion/Jira/Linear/GitHub Projects.

Table Legend

  • Doc: mandatory artifact to create/update for the checklist item
  • Owner: accountable role (PM/BA/Eng/QA/DevOps/Client)
  • Gate: where this item is required to proceed (Discovery / Scope Freeze / Build Start / Release)

0) Contract Baseline

# Checklist item Document(s) Owner Gate Status Link
0.1 Client SOW received (signed or draft) Client SOW vX.Y PM/BA Discovery
0.2 SOW review completed: scope boundaries, deliverables, assumptions, exclusions, acceptance, timeline, commercials SOW Review Notes (1–2 pages) PM/BA Discovery
0.3 Open questions captured and sent to client Open Questions Log PM/BA Discovery
0.4 Risks/unknowns logged (access, data, vendors, integrations) RAID Log (Risks/Assumptions/Issues/Dependencies) PM/BA Discovery
0.5 Acceptance approach aligned (how client signs off, what evidence required) Acceptance & Sign‑off Procedure (1 page) PM/BA + Client Discovery

1) Feature R&D (Within SOW Boundary)

# Checklist item Document(s) Owner Gate Status Link
1.1 Feature research completed (benchmarks/parity/ROI hypotheses) Feature Research Report (sources + findings) PM/BA Discovery
1.2 Candidate features catalogued with value + dependency + effort range + risk Feature Briefs (1‑pager each, optional but ideal) PM/BA Discovery
1.3 Constraints captured (manpower, timeline, tech constraints, vendor constraints) Constraints & Assumptions Register PM/BA + Tech Lead Discovery

2) Feature Decision Matrix + Approval (Scope Selection)

# Checklist item Document(s) Owner Gate Status Link
2.1 Decision matrix prepared (ROI vs effort vs risk vs dependency vs strategic value) Feature Decision Matrix (sheet) PM/BA Scope Freeze
2.2 MVP/Phase 1 feature list finalized Phase Scope List — MVP (appendix OK) PM/BA + Client Scope Freeze
2.3 Phase 2 feature list finalized Phase Scope List — Phase 2 (appendix OK) PM/BA + Client Scope Freeze
2.4 Explicit Out‑of‑Scope list written Out‑of‑Scope Register PM/BA Scope Freeze
2.5 Approval recorded (date + approvers + notes) Scope Approval Record (minutes/email/sign‑off page) PM/BA + Client Scope Freeze

3) PRD (Scope‑Frozen Execution Blueprint)

# Checklist item Document(s) Owner Gate Status Link
3.1 PRD created/updated from approved matrix PRD v1.0 (scope‑frozen) PM/BA Scope Freeze
3.2 Each feature has testable requirements + acceptance criteria PRD — Requirements & Acceptance Criteria section/appendix PM/BA + QA Lead Scope Freeze
3.3 Non‑functional requirements locked (perf, reliability, security, observability) NFR Appendix (or SRS‑lite section) PM/BA + Tech Lead Scope Freeze
3.4 Change control policy included (“no scope without CR”) Change Control Policy (1 page; PRD section OK) PM/BA Scope Freeze
3.5 PRD sign‑off captured PRD Sign‑off Record PM/BA + Client Scope Freeze

4) Estimation + Delivery Plan (Budgeting & Timeline)

# Checklist item Document(s) Owner Gate Status Link
4.1 Engineering estimates produced from PRD (epics/stories) Estimation Sheet (feature → effort → owner) Tech Lead Build Start
4.2 Timeline + milestones finalized Delivery Roadmap / Release Plan PM/BA + Tech Lead Build Start
4.3 Backlog created and mapped to PRD requirement IDs Backlog Mapping (PRD FR‑IDs → Epics/Stories) PM/BA + Tech Lead Build Start
4.4 QA effort included (test types + envs + regression scope) QA Plan (MVP) QA Lead Build Start
4.5 DevOps effort included (CI/CD, envs, monitoring, runbooks) DevOps Plan DevOps/Tech Lead Build Start
4.6 Budget baseline computed (people + infra + tools) Budget & Cost Model (build + run) PM/Finance + Tech Lead Build Start

5) SOW Addendum / Change Order (ONLY If Mismatch)

# Checklist item Document(s) Owner Gate Status Link
5.1 PRD vs SOW gap check completed Scope‑to‑Contract Trace (PRD↔SOW mapping table) PM/BA Build Start
5.2 If scope/timeline/cost/acceptance changed → Change Order drafted Change Order / SOW Addendum #N PM/BA + Client Build Start
5.3 Commercials updated if impacted (milestones/payment terms) Revised Milestone/Payment Schedule (if needed) PM/Finance + Client Build Start
5.4 Addendum signed by client Signed Addendum PM/BA + Client Build Start

Rule: If PRD only clarifies and stays within SOW with no commercial/timeline change, you may mark section 5 as N/A.


6) Build Readiness Gate (Start Development)

# Checklist item Document(s) Owner Gate Status Link
6.1 Architecture sufficient for Sprint 1 HLD (C4/System Context + components) Solution Architect/Tech Lead Build Start
6.2 Core flows designed (happy path + failure path) LLD (sequence diagrams + edge cases) Tech Lead Build Start
6.3 Interfaces locked for MVP OpenAPI Spec + Integration Spec (partners) Tech Lead Build Start
6.4 Data model ready for MVP ERD + Data Dictionary Tech Lead Build Start
6.5 Security baseline agreed (authN/authZ, threat model, PII handling) Security Requirements / Threat Model Security/Tech Lead Build Start
6.6 Observability defined (logs/metrics/traces, dashboards, alerts) Observability Plan DevOps/Tech Lead Build Start

7) Release Readiness Gate (Ship MVP)

# Checklist item Document(s) Owner Gate Status Link
7.1 Test execution completed with evidence Test Report (results + defects + sign‑off) QA Lead Release
7.2 Performance checks passed (as per NFRs) Perf Report (p95/p99, load profile) QA/Tech Lead Release
7.3 Security checks passed (baseline) Security Test Summary (SAST/DAST + fixes) Security/Tech Lead Release
7.4 Runbooks + oncall response prepared Runbook / Ops Playbook DevOps Release
7.5 Go/No‑Go completed and approved Go/No‑Go Checklist (signed) PM/Tech Lead/Client Release
7.6 Release notes prepared Release Notes PM/BA Release

Quick Copy Section (Owners)

  • PM/BA: scope, approvals, PRD, change control, roadmap, client coordination
  • Tech Lead/Solution Architect: HLD/LLD, estimates, API/data/security/observability alignment
  • QA Lead: test strategy/plan, execution, reports
  • DevOps: CI/CD, environments, monitoring, runbooks
  • Client: scope sign‑off, addendum sign‑off, release acceptance